[IndianaTrails] ballast
williamd@bloomington.in.gov
williamd at bloomington.in.gov
Fri Apr 21 05:28:50 PDT 2006
Good luck to you Bruce. IDEM will require any excavated or removed
ballast on our trail in Bloomington to be land filled as "special waste".
Any ballast remaining will have to be covered with 12" of fill/soil. The
reason is that the remnant material in the ballast, coal ash and cinder,
is hazardous. In some situations, the material can be utilized as
structural fill, but only if it is capped with an impervious
(asphalt/concrete)surface. This is a very short explanation for what will
be a very expensive process and cost for remediation - on Bloomington's
downtown trail project - and I suspect other trail builders in the future
as well.
Dave Williams
Bloomington
--------------------------------------------------------------------------
From: Bruce Fingerhut [mailto:bruce at sugardog.com]
Sent: Thursday, April 20, 2006 10:32 PM
To: list at indianatrails.org
Subject: [IndianaTrails] ballast
A quick question to all who are working on a trail or have completed a
trail. Has any had any luck selling the ballast? We have 16 miles of
rail banked right of way with heavy ballast and a good portion of the
trail had double tracks. Any information would be appreciated.
Thanks for your help.
Bruce Fingerhut
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://indianatrails.org/pipermail/list_indianatrails.org/attachments/20060421/a1aa7822/attachment.htm
More information about the List
mailing list